← Leonia Renovation

Gutting the Attic Down to Frame

20 photos · attic

The attic was an unfinished mess — lath, dead insulation, old knob-and-tube remnants, plank floor full of nails. Worse, one of the structural beams had a bad split at a joint. I cleared everything out, sistered rafters where they were undersized, reinforced the ridge with bolted plates, and got the floor back patched before any new framing went in.

  1. Original attic — lath wall, gable window, exposed rafters. Storage at best, nothing finished. Before

    Original attic — lath wall, gable window, exposed rafters. Storage at best, nothing finished.

    attic
  2. Same view from another angle. Plank sheathing, no insulation, gable window at the end. Before

    Same view from another angle. Plank sheathing, no insulation, gable window at the end.

    attic
  3. Roof decking nails poking through and old wiring strung along the planks. All of it had to go. Before

    Roof decking nails poking through and old wiring strung along the planks. All of it had to go.

    attic
  4. Cleared-out attic with a work light running. Quiet stage before framing started. Before

    Cleared-out attic with a work light running. Quiet stage before framing started.

    attic
  5. Cracked structural beam at one of the joints. Sistered and bolted before I trusted anything to it. Before

    Cracked structural beam at one of the joints. Sistered and bolted before I trusted anything to it.

    attic
  6. Stripped to plank floors and bare rafters under a single work light. Demo dust everywhere. During

    Stripped to plank floors and bare rafters under a single work light. Demo dust everywhere.

    attic
  7. Fisheye camera shot through the framing once the lath came off. Wide-open envelope. During

    Fisheye camera shot through the framing once the lath came off. Wide-open envelope.

    attic
  8. Same gut stage from the other end. Plank floors, exposed rafters, work light. During

    Same gut stage from the other end. Plank floors, exposed rafters, work light.

    attic
  9. Engineered roof trusses exposed after the sheathing came off. Cleaner than I expected. During

    Engineered roof trusses exposed after the sheathing came off. Cleaner than I expected.

    attic
  10. Old insulation pulled out, shop vac running, trash bags filling up. During

    Old insulation pulled out, shop vac running, trash bags filling up.

    attic
  11. Last of the old batts stacked along the rafters before they went out for haul-away. During

    Last of the old batts stacked along the rafters before they went out for haul-away.

    attic
  12. Pulled some floorboards to access the joist bays and run new wiring before the floor closed back up. During

    Pulled some floorboards to access the joist bays and run new wiring before the floor closed back up.

    attic
  13. Sister boards bolted alongside the original rafters where the framing was undersized. During

    Sister boards bolted alongside the original rafters where the framing was undersized.

    attic
  14. Ridge beam with the bolted plate reinforcement and walls down to studs. During

    Ridge beam with the bolted plate reinforcement and walls down to studs.

    attic
  15. Ridge beam reinforcement plates in with active work materials still scattered around. During

    Ridge beam reinforcement plates in with active work materials still scattered around.

    attic
  16. Mid-cleanup with the ridge and rafters all open. Floor still original plank. During

    Mid-cleanup with the ridge and rafters all open. Floor still original plank.

    attic
  17. Empty attic under work lights once the last of the debris came out. During

    Empty attic under work lights once the last of the debris came out.

    attic
  18. Shop vac and ladder staged for the next phase. Floor was as clean as it was going to get. During

    Shop vac and ladder staged for the next phase. Floor was as clean as it was going to get.

    attic
  19. Black vapor barrier draped along the slope before I started building down both sides. During

    Black vapor barrier draped along the slope before I started building down both sides.

    attic
  20. Patched the floorboards back in after the wiring was done. Ready for finish work. During

    Patched the floorboards back in after the wiring was done. Ready for finish work.

    attic